WAPA-DSW-2024-G4
550 MW hybrid in Mohave, AZ · In queue since April 2024 · Proposed COD December 2027
550 MW
Capacity
1
Components
Solar
2y 1m
In Queue
—
IA Status
COD target: 2027
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
The proposed WAPA-DSW-2024-G4 project is a 550 MW hybrid solar and battery energy storage development project located in Mohave County, Arizona. The project consists of 550 MW of solar generation capacity. It is listed in the WAPA Desert Southwest Region interconnection queue as of April 30, 2024, with a proposed commercial operation date of December 31, 2027.
The project is listed as active in the interconnection queue. The interconnection point of contact is the Topock 230kV substation.
Generated from interconnection queue and public data sources
State
AZ
County
Mohave
Grid Region
Mountain West
Market
—
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-DSW
Service Type
—
Point of Interconnection
Topock 230kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.