WAPA-DSW-2024-G5
300 MW generation in Mohave, AZ · In queue since August 2024 · Proposed COD December 2029
300 MW
Capacity
1
Components
Wind
1y 9m
In Queue
—
IA Status
COD target: 2029
Total Duration
5y 4m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-01
WAPA-DSW-2024-G5 is a proposed wind energy project located in Mohave County, Arizona, within the Western region. The project, with a total capacity of 300 MW, is being developed under the auspices of the WAPA Desert Southwest Region. It consists of 300 MW of wind generation capacity.
The project is currently active in the WAPA-DSW interconnection queue, having entered the queue on August 15, 2024. The proposed commercial operation date is December 1, 2029.
Generated from interconnection queue and public data sources
State
AZ
County
Mohave
Grid Region
Mountain West
Market
—
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-DSW
Service Type
—
Point of Interconnection
Mead _x0013_ Peacock 345kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.