WAPA-DSW-2024-G6
50 MW generation in Mohave, AZ · In queue since August 2024 · Proposed COD March 2027
50 MW
Capacity
1
Components
Gas
1y 9m
In Queue
—
IA Status
COD target: 2027
Total Duration
2y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-03-01
The proposed project, identified as WAPA-DSW-2024-G6, is a 50 MW natural gas-fired generation project located in Mohave County, Arizona. The project is in the West region and is being proposed within the Western Area Power Administration (WAPA) Desert Southwest Region interconnection queue. The queue entry date is August 23, 2024, with a proposed commercial operation date of March 1, 2027.
The project is currently listed as active in the interconnection queue. The point of interconnection (POI) is the Griffith Switchyard 230kV. There is no information available regarding the developer, interconnection agreement status, or news coverage.
Generated from interconnection queue and public data sources
State
AZ
County
Mohave
Grid Region
Mountain West
Market
—
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-DSW
Service Type
—
Point of Interconnection
Griffith Switchyard 230kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project WAPA-DSW-2024-G6