WAPA-IS-GI-1404
383 MW generation in Billings, ND · In queue since May 2014
383 MW
Capacity
1
Components
Wind
12 years
In Queue
In Progress (unknown study)
IA Status
Total Duration
12 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
WAPA-IS-GI-1404 is a proposed wind generation project with a total capacity of 383 MW, located in Billings County, North Dakota. The project is in the West Area Power Administration Integrated System (WAPA-IS) interconnection queue, with a queue entry date of May 14, 2014. Its point of interconnection is the Charlie Creek 345kV substation.
The interconnection agreement for the project is currently listed as "In Progress (unknown study)". The developer is unknown. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
ND
County
Billings
Grid Region
Mountain West
Market
—
Developer
—
Utility
WAPA/BEPC/HCPD Integrated System
Entity
WAPA-IS
Service Type
—
Point of Interconnection
Charlie Creek 345kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.