WAPA-IS-GI-1501
200 MW generation in Bon Homme, SD · In queue since February 2015
200 MW
Capacity
1
Components
Wind
11y 3m
In Queue
In Progress (unknown study)
IA Status
Total Duration
11y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
WAPA-IS-GI-1501 is a proposed 200 MW wind generation project located in Bon Homme County, South Dakota. The project is in the West region and is being developed within the WAPA/BEPC/HCPD Integrated System, under the entity WAPA-IS. It entered the WAPA-IS interconnection queue on February 24, 2015. The project's interconnection agreement status is listed as "In Progress (unknown study)".
The proposed project consists of 200 MW of wind generation capacity. Its point of interconnection is the Ft. Randall-Utica Junction 230kV line. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
SD
County
Bon Homme
Grid Region
Mountain West
Market
—
Developer
—
Utility
WAPA/BEPC/HCPD Integrated System
Entity
WAPA-IS
Service Type
—
Point of Interconnection
Ft. Randall-Utica Junction 230kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project WAPA-IS-GI-1501