WAPA-IS-GI-1505
99 MW generation in Brown, SD · In queue since April 2015
99 MW
Capacity
1
Components
Wind
11y 1m
In Queue
In Progress (unknown study)
IA Status
Total Duration
11y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
WAPA-IS-GI-1505 is a proposed wind generation project with a total capacity of 99 MW, located in Brown County, South Dakota. The project is being developed within the WAPA/BEPC/HCPD Integrated System and interconnected via the WAPA-IS utility. It entered the interconnection queue on April 8, 2015.
The project's interconnection status is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Groton 115kV substation.
Generated from interconnection queue and public data sources
State
SD
County
Brown
Grid Region
Mountain West
Market
—
Developer
—
Utility
WAPA/BEPC/HCPD Integrated System
Entity
WAPA-IS
Service Type
—
Point of Interconnection
Groton 115kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project WAPA-IS-GI-1505