WAPA-IS-GI-1509
150 MW generation in Stark, ND · In queue since September 2015
150 MW
Capacity
1
Components
Wind
10y 8m
In Queue
In Progress (unknown study)
IA Status
Total Duration
10y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
WAPA-IS-GI-1509 is a proposed wind generation project with a total capacity of 150 MW. The project is located in Stark County, North Dakota, and interconnects to the WAPA/BEPC/HCPD Integrated System, specifically at the Belfield-Rhame 230kV point of interconnection. The project entered the WAPA-IS interconnection queue on September 30, 2015.
The interconnection agreement for WAPA-IS-GI-1509 is currently listed as "In Progress (unknown study)". The developer is unknown.
Generated from interconnection queue and public data sources
State
ND
County
Stark
Grid Region
Mountain West
Market
—
Developer
—
Utility
WAPA/BEPC/HCPD Integrated System
Entity
WAPA-IS
Service Type
—
Point of Interconnection
Belfield-Rhame 230kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project WAPA-IS-GI-1509