Project WAPA-MPP-2023-MP1 — Project Summary

Queue ID
WAPA-MPP-2023-MP1
Capacity
500 MW
Technology
Solar+Battery
Status
active
Location
Yavapai, AZ
Region
West
Developer
IA Status

WAPA-MPP-2023-MP1

WAPA-MPP-2023-MP1BetaActiveSolarBatteryWAPA-MPPLBNL

500 MW hybrid in Yavapai, AZ · In queue since February 2023 · Proposed COD December 2026

500 MW

Capacity

1

Components

Solar

3y 3m

In Queue

IA Status

COD target: 2026

Interconnection

Total Duration

3y 10m

Pre-Study0%
Queue EntryFeb 3, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-01

About

WAPA-MPP-2023-MP1 is a proposed 500 MW hybrid solar and battery project located in Yavapai County, Arizona. The development project, located in the West region, consists of 500 MW of solar capacity. The project is listed in the WAPA Desert Southwest Region interconnection queue as of February 3, 2023, with a proposed commercial operation date of December 1, 2026.

The project is interconnected to the Mead-Perkins 500kV point of interconnection and is currently listed as active in the interconnection queue of WAPA-MPP. There has been recent news coverage of the project.

Generated from interconnection queue and public data sources

Project Details

State

AZ

County

Yavapai

Grid Region

Mountain West

Market

Developer

Utility

WAPA Desert Southwest Region

Entity

WAPA-MPP

Service Type

Point of Interconnection

Mead-Perkins 500kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
PALOVERDE
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.