WAPA-MPP-2023-MP1
500 MW hybrid in Yavapai, AZ · In queue since February 2023 · Proposed COD December 2026
500 MW
Capacity
1
Components
Solar
3y 3m
In Queue
—
IA Status
COD target: 2026
Total Duration
3y 10m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-01
WAPA-MPP-2023-MP1 is a proposed 500 MW hybrid solar and battery project located in Yavapai County, Arizona. The development project, located in the West region, consists of 500 MW of solar capacity. The project is listed in the WAPA Desert Southwest Region interconnection queue as of February 3, 2023, with a proposed commercial operation date of December 1, 2026.
The project is interconnected to the Mead-Perkins 500kV point of interconnection and is currently listed as active in the interconnection queue of WAPA-MPP. There has been recent news coverage of the project.
Generated from interconnection queue and public data sources
State
AZ
County
Yavapai
Grid Region
Mountain West
Market
—
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-MPP
Service Type
—
Point of Interconnection
Mead-Perkins 500kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN