WAPA-MPP-2023-MP2
600 MW hybrid in Mohave, AZ · In queue since March 2023 · Proposed COD June 2026
600 MW
Capacity
1
Components
Solar
3y 2m
In Queue
—
IA Status
COD target: 2026
Total Duration
3y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-06-23
WAPA-MPP-2023-MP2 is a proposed 600 MW hybrid solar and battery project located in Mohave County, Arizona. The project, which consists of 600 MW of solar capacity, is in the WAPA Desert Southwest Region interconnection queue (WAPA-MPP) with an entry date of March 23, 2023. The proposed commercial operation date is June 23, 2026.
The project is currently listed as active in the interconnection queue. The point of interconnection is the Mead-Perkins 500kV line.
Generated from interconnection queue and public data sources
State
AZ
County
Mohave
Grid Region
Mountain West
Market
—
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-MPP
Service Type
—
Point of Interconnection
Mead-Perkins 500kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.