WAPA-MPP-2024-MP1
500 MW storage in Mohave, AZ · In queue since January 2024 · Proposed COD December 2028
500 MW
Capacity
1
Components
Battery
2y 4m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
WAPA-MPP-2024-MP1 is a proposed 500 MW battery storage project located in Mohave County, Arizona. The project is in the West region and is being developed within the WAPA Desert Southwest Region interconnection queue, under the entity WAPA-MPP. The project entered the queue on January 5, 2024, and has a proposed commercial operation date of December 1, 2028.
The project is interconnected at the Mead 500kV Substation. As of the latest data, the project's interconnection status is listed as active.
Generated from interconnection queue and public data sources
State
AZ
County
Mohave
Grid Region
Mountain West
Market
—
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-MPP
Service Type
—
Point of Interconnection
Mead 500kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project WAPA-MPP-2024-MP1