WAPA-RM-2008-G9
90 MW generation in Yuma, CO · In queue since March 2008 · Proposed COD October 2019
90 MW
Capacity
1
Components
Wind
18y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2019
Total Duration
11y 7m
Schedule
80 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2019-10-01
The proposed WAPA-RM-2008-G9 project is a 90 MW wind generation development in Yuma County, Colorado. The project, located in the Western region, is being developed within the Western Area Power Administration - Rocky Mountain Region (WAPA-RM) and is listed in the LAPT interconnection queue.
The project entered the queue on March 28, 2008, with a proposed commercial operation date of October 1, 2019. Its interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Wray Substation 115-kV.
Generated from interconnection queue and public data sources
State
CO
County
Yuma
Grid Region
Mountain West
Market
—
Developer
—
Utility
LAPT
Entity
WAPA-RM
Service Type
—
Point of Interconnection
Wray Sub. 115-kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project WAPA-RM-2008-G9