WAPA-RM-2018-G6
360 MW hybrid in San Juan, NM · In queue since September 2018 · Proposed COD December 2022
360 MW
Capacity
1
Components
Solar
7y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Total Duration
4y 3m
Schedule
41 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-12-31
WAPA-RM-2018-G6 is a proposed 360 MW hybrid solar and battery project located in San Juan County, New Mexico. The project is listed in the Western Area Power Administration - Rocky Mountain Region (WAPA-RM) interconnection queue, with an entry date of September 10, 2018. The proposed commercial operation date is December 31, 2022.
The interconnection agreement status is listed as "In Progress (unknown study)". The project, which will interconnect at the Shiprock 345-kV Substation, is being developed within the Colorado River Commission Municipal Participants (CRCM) balancing authority area. The project consists of 360 MW of solar capacity.
Generated from interconnection queue and public data sources
State
NM
County
San Juan
Grid Region
Mountain West
Market
—
Developer
—
Utility
CRCM
Entity
WAPA-RM
Service Type
—
Point of Interconnection
Shiprock 345-kV Sub
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.