WAPA-RM-2019-G1
252 MW generation in Jackson, CO · In queue since November 2018 · Proposed COD December 2021
252 MW
Capacity
1
Components
Wind
7y 6m
In Queue
IA Executed
IA Status
COD target: 2021
Total Duration
3y 1m
Schedule
53 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2021-12-31
The proposed WAPA-RM-2019-G1 project is a 252 MW wind generation facility located in Jackson County, Colorado. The project is being developed within the Western Area Power Administration - Rocky Mountain Region (WAPA-RM) queue, with an interconnection queue entry date of November 7, 2018. The proposed commercial operation date is December 31, 2021, and the interconnection agreement has been executed.
The project is interconnected to the Craig - Ault 345-kV point of interconnection. The utility associated with the project is CRCM. The project is listed as having an active status in the interconnection queue.
Generated from interconnection queue and public data sources
State
CO
County
Jackson
Grid Region
Mountain West
Market
—
Developer
—
Utility
CRCM
Entity
WAPA-RM
Service Type
—
Point of Interconnection
Craig - Ault 345-kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project WAPA-RM-2019-G1