WAPA-RM-2019-G2
252 MW generation in Jackson, CO · In queue since November 2018 · Proposed COD December 2022
252 MW
Capacity
1
Components
Wind
7y 6m
In Queue
IA Executed
IA Status
COD target: 2022
Total Duration
4y 1m
Schedule
41 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2022-12-31
The proposed WAPA-RM-2019-G2 project is a 252 MW wind generation facility located in Jackson County, Colorado. The project is being developed within the Western Area Power Administration - Rocky Mountain Region (WAPA-RM) interconnection queue under the utility CRCM. The project entered the queue on November 7, 2018, with a proposed commercial operation date of December 31, 2022.
The interconnection agreement for the WAPA-RM-2019-G2 project has been executed. The point of interconnection is the Craig - Ault 345-kV line. The project consists of 252 MW of wind generation capacity.
Generated from interconnection queue and public data sources
State
CO
County
Jackson
Grid Region
Mountain West
Market
—
Developer
—
Utility
CRCM
Entity
WAPA-RM
Service Type
—
Point of Interconnection
Craig - Ault 345-kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS