WAPA-RM-2019-G3
150 MW generation in Weld, CO · In queue since December 2018 · Proposed COD December 2021
150 MW
Capacity
1
Components
Solar
7y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2021
Total Duration
3 years
Schedule
54 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-12-01
The proposed WAPA-RM-2019-G3 project is a 150 MW solar generation project located in Weld County, Colorado. The project is in the Western Area Power Administration - Rocky Mountain Region (WAPA-RM) interconnection queue, with an entry date of December 12, 2018. The proposed commercial operation date is December 1, 2021.
The interconnection agreement (IA) status is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Ault 230-kV substation. The interconnecting utility is CRCM.
Generated from interconnection queue and public data sources
State
CO
County
Weld
Grid Region
Mountain West
Market
—
Developer
—
Utility
CRCM
Entity
WAPA-RM
Service Type
—
Point of Interconnection
Ault 230-kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project WAPA-RM-2019-G3