WAPA-RM-2023-G10.1
90 MW storage in Coconino, AZ · In queue since October 2023 · Proposed COD January 2026
90 MW
Capacity
1
Components
Battery
2y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
2y 3m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-01-09
WAPA-RM-2023-G10.1 is a proposed 90 MW battery storage project located in Coconino County, Arizona. The project is being developed within the Western Area Power Administration - Rocky Mountain Region (WAPA-RM) balancing authority area and is interconnected via the CRCM utility.
The project entered the interconnection queue on October 3, 2023, with a proposed commercial operation date of January 9, 2026. Its interconnection agreement status is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
AZ
County
Coconino
Grid Region
Mountain West
Market
—
Developer
—
Utility
CRCM
Entity
WAPA-RM
Service Type
—
Point of Interconnection
Navajo - Glen Canyon 230kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project WAPA-RM-2023-G10.1