WAPA-RM-2023-G3
150 MW generation in Albany, WY · In queue since November 2022 · Proposed COD December 2026
150 MW
Capacity
1
Components
Solar
3y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-01
The proposed WAPA-RM-2023-G3 project is a 150 MW solar generation project located in Albany County, Wyoming. The project is being developed within the Western Area Power Administration - Rocky Mountain Region (WAPA-RM) and is interconnected with the LAPT utility.
The project entered the interconnection queue on November 18, 2022, with a proposed commercial operation date of December 1, 2026. Its interconnection agreement status is currently listed as "In Progress (unknown study)". The point of interconnection is the Northpark - Terry Ranch 230-kV line.
Generated from interconnection queue and public data sources
State
WY
County
Albany
Grid Region
Mountain West
Market
—
Developer
—
Utility
LAPT
Entity
WAPA-RM
Service Type
—
Point of Interconnection
Northpark - Terry Ranch 230-kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.