WAPA-RM-2023-G7
200 MW generation in Jackson, CO · In queue since July 2023 · Proposed COD December 2026
200 MW
Capacity
1
Components
Solar
2y 10m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 5m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
WAPA-RM-2023-G7 is a proposed 200 MW solar generation project located in Jackson County, Colorado. The project is being developed within the Western Area Power Administration - Rocky Mountain Region (WAPA-RM) queue and interconnected via the 345kV Ault-Craig transmission line. The queue entry date is July 24, 2023, with a proposed commercial operation date of December 31, 2026.
The interconnection agreement (IA) status for the project is currently listed as "In Progress (unknown study)". The project is listed under the utility CRCM. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
CO
County
Jackson
Grid Region
Mountain West
Market
—
Developer
—
Utility
CRCM
Entity
WAPA-RM
Service Type
—
Point of Interconnection
345kV Ault-Craig transmission line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project WAPA-RM-2023-G7