WAPA-RM-2024-G2
150 MW hybrid in Weld, CO · In queue since September 2024 · Proposed COD December 2028
150 MW
Capacity
1
Components
Solar
1y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
4y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
The proposed WAPA-RM-2024-G2 project is a 150 MW hybrid solar and battery energy storage development in Weld County, Colorado. The project consists of 150 MW of solar photovoltaic generation. It is located in the Western Area Power Administration - Rocky Mountain Region (WAPA-RM) balancing authority area.
The project is actively listed in the LAPT interconnection queue as of September 18, 2024, with a proposed commercial operation date of December 1, 2028. Its interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Archer - Ault 230kV line.
Generated from interconnection queue and public data sources
State
CO
County
Weld
Grid Region
Mountain West
Market
—
Developer
—
Utility
LAPT
Entity
WAPA-RM
Service Type
—
Point of Interconnection
Archer - Ault 230kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project WAPA-RM-2024-G2