WAPA-SN-2019-G1
300 MW hybrid in Butte, CA · In queue since August 2019 · Proposed COD December 2027
300 MW
Capacity
1
Components
Solar
6y 9m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
8y 4m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
WAPA-SN-2019-G1 is a proposed 300 MW hybrid solar and battery project located in Butte County, California. The project, which consists of 300 MW of solar capacity, is in the WAPA Sierra Nevada interconnection queue, with an entry date of August 8, 2019. The proposed commercial operation date is December 31, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the Cottonwood-Roseville 230-kV Transmission Line. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
CA
County
Butte
Grid Region
Mountain West
Market
—
Developer
—
Utility
WAPA Sierra Nevada
Entity
WAPA-SN
Service Type
—
Point of Interconnection
Cottonwood-Roseville 230-kV Transmission Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project WAPA-SN-2019-G1