WAPA-SN-2023-G1
800 MW hybrid in Fresno, CA · In queue since March 2023 · Proposed COD June 2028
800 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
5y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-01
WAPA-SN-2023-G1 is a proposed 800 MW hybrid solar and battery project in Fresno County, California. The project, located in the West region, consists of 800 MW of solar capacity. It is being proposed within the WAPA Sierra Nevada interconnection queue, with an entry date of March 1, 2023, and a proposed commercial operation date of June 1, 2028. The interconnection agreement status is listed as "In Progress (unknown study)".
The development project has been the subject of recent news coverage, with three articles categorized as regulatory matters.
Generated from interconnection queue and public data sources
State
CA
County
Fresno
Grid Region
Mountain West
Market
—
Developer
—
Utility
WAPA Sierra Nevada
Entity
WAPA-SN
Service Type
—
Point of Interconnection
New Point 500-kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-14