WAPA-SN-2023-G2
800 MW hybrid in Fresno, CA · In queue since March 2023 · Proposed COD June 2028
800 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
5y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-01
WAPA-SN-2023-G2 is a proposed 800 MW hybrid solar and battery project located in Fresno County, California. The development project consists of 800 MW of solar capacity. It is listed in the WAPA Sierra Nevada interconnection queue as of March 1, 2023, with a proposed commercial operation date of June 1, 2028. The interconnection agreement status is currently listed as "In Progress (unknown study)".
The project's point of interconnection is designated as "New Point 500-kV". The project has appeared in recent news coverage regarding renewable energy development in the Western United States.
Generated from interconnection queue and public data sources
State
CA
County
Fresno
Grid Region
Mountain West
Market
—
Developer
—
Utility
WAPA Sierra Nevada
Entity
WAPA-SN
Service Type
—
Point of Interconnection
New Point 500-kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.