WAPA-SN-2023-G4
100 MW hybrid in Butte, CA · In queue since August 2023 · Proposed COD March 2028
100 MW
Capacity
1
Components
Solar
2y 9m
In Queue
System Impact Study
IA Status
COD target: 2028
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-03-01
The proposed WAPA-SN-2023-G4 project is a 100 MW solar and battery hybrid development in Butte County, California. The project consists of 100 MW of solar generation capacity. It is located in the Western region and is being proposed within the WAPA Sierra Nevada interconnection queue, with an entry date of August 22, 2023.
The project's proposed commercial operation date is March 1, 2028. Its interconnection status is currently in the System Impact Study phase. The point of interconnection is the Cottonwood-Roseville 230-kV Transmission Line.
Generated from interconnection queue and public data sources
State
CA
County
Butte
Grid Region
Mountain West
Market
—
Developer
—
Utility
WAPA Sierra Nevada
Entity
WAPA-SN
Service Type
—
Point of Interconnection
Cottonwood-Roseville 230-kV Transmission Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project WAPA-SN-2023-G4