WAPA-SN-2024-G2
125 MW hybrid in Shasta, CA · In queue since November 2024 · Proposed COD December 2028
125 MW
Capacity
1
Components
Solar
1y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
The WAPA-SN-2024-G2 development project is a proposed 125 MW solar and battery hybrid project located in Shasta County, California. The project is listed in the WAPA Sierra Nevada interconnection queue as of November 1, 2024, with a proposed commercial operation date of December 31, 2028.
The interconnection agreement for the project is currently listed as "In Progress (unknown study)". The point of interconnection is the Round Mtn-Cottonwood 230-kV Transmission Line. Recent news coverage of the project may exist.
Generated from interconnection queue and public data sources
State
CA
County
Shasta
Grid Region
Mountain West
Market
—
Developer
—
Utility
WAPA Sierra Nevada
Entity
WAPA-SN
Service Type
—
Point of Interconnection
Round Mtn-Cottonwood 230-kV Transmission Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project WAPA-SN-2024-G2