200 MW Solar operating in Kent, TX — Electric Reliability Council of Texas, Inc.
200 MW
Nameplate Capacity
1
Generators
unit
Solar Photovoltaic
Technology
2024
Operating Since
Owner data does not fully agree across sources.
EIA typically reports the operating utility, while GEM resolves to the financial owner or parent corporation. Both can be correct.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Texas Solar Nova 2, LLC | Clearway Energy Group LLC | — |
| Owner(s) | Texas Solar Nova 2, LLC | Clearway Energy | — |
| Status | Operating | operating | — |
Texas Solar Nova 2 is a 200 MW solar photovoltaic power plant located in Kent County, Texas. The plant, which began operating in 2024, utilizes single-axis tracking technology. It is owned by Clearway Energy and operated by Texas Solar Nova 2, LLC. The plant is interconnected to the Electric Reliability Council of Texas (ERCOT) grid, within the TRE NERC region.
The facility's latest annual generation was 562,730 MWh, resulting in a capacity factor of 32.1%. Texas Solar Nova 2 ranks as the 107th largest solar plant in Texas out of 192, and 206th nationally out of 639. Financial data is available for the plant, sourced from LBNL Solar.
Generated from EIA, GEM, and public data sources
ISO/RTO
ERCOT
Market
ISO/RTO Member
NERC Region
TRE — Texas Reliability Entity
Balancing Authority
33.7K MWh
Latest Month
562.7K MWh
Annual Generation
32.1%
Capacity Factor
Data from 2024
$31.6/MWh
LCOE
Market Position
ISO/RTO Market
ERCOT
LMP Node
NOVA1SLR_ALL
Pricing Hub
HB_WEST
Alt. Hub / Zone
LZ_WEST
Location Type
Resource Node
Node Source
Curated node match
Last updated 2026-03-26
View all articlesElectric Reliability Council of Texas, Inc. (ERCO)
Grid Voltage
138.0 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Independent Power Producer
Sector
IPP Non-CHP