Search plants, projects, owners, and states
79.6 MW Solar planned in York, PA — PJM Interconnection, LLC
79.6 MW
Nameplate Capacity
1
Generators
unit
Solar Photovoltaic
Technology
Planned: —
Planned Operation
Coordinates
40.0901, -76.7395
County
York, PA
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Strinestown Solar, LLC | — | — |
| Owner(s) | Strinestown Solar, LLC | — | — |
| Status | Planned | pre-construction | — |
Strinestown Solar is a 79.6 MW solar photovoltaic power plant located in York County, Pennsylvania. The plant, owned and operated by Strinestown Solar, LLC, utilizes fixed-tilt solar tracking technology. It is the 13th largest solar plant in Pennsylvania out of 87, and ranks 758th nationally among 7,108 solar facilities. The plant has one generator and its primary fuel source is solar energy.
Strinestown Solar operates within the PJM Interconnection, LLC balancing authority and the RFC NERC region. Recent news coverage related to the plant has focused on regulatory matters.
Generated from EIA, GEM, and public data sources
ISO/RTO
PJM
Market
ISO/RTO Member
NERC Region
RFC
Balancing Authority
No generation data available for this plant.
2023
$2,584/kW
Est. Construction Cost
Total estimated cost: $205.7M
Point of Interconnection
Nearest Substation
Cly Substation · 115 kV
Substation Distance
< 10 km
Operator
Met-Ed
Coord Source
OSM spatial
Market Position
ISO/RTO Market
PJM
LMP Node
METED, ZIONSVIE115KV 1B12, 49498
Pricing Hub
WESTERN HUB
Node Source
EIA-860 direct report
Last updated 2026-03-26
View all articlesNo ask pi reports yet for this entity.
ask pi about Strinestown SolarPJM Interconnection, LLC (PJM)
Grid Voltage
115.0 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Independent Power Producer
Sector
IPP Non-CHP